Tragedy in Dymer: 79-Year-Old Woman Dies in Hospital Following Enemy Attack Sky News Documentary on Ukrainian National Guardsmen Wins International Emmy Award The 'Carthage-2' Case: NABU Releases Details of Searches at SBU Major General Duka's Residence Ukrainian MFA Responds to Libya Regarding the Destruction of the Russian Corvette in Benghazi Foreign Currencies Rise in Ukraine: New Exchange Rates Recorded in Banks and Exchange Offices Uncertainty Over NMT-2027: 'Parents SOS' Highlights Risks of Admission Rules Delay Ukrainian MFA Responds to Libya Over Destroyed Russian Corvette Russia Plans to Launch Satellite with Nuclear Warhead Why Electricity Bills Don't Decrease During Power Outages Ukraine at UN: Withdrawal demands are not a path to peace Tragedy in Dymer: 79-Year-Old Woman Dies in Hospital Following Enemy Attack Sky News Documentary on Ukrainian National Guardsmen Wins International Emmy Award The 'Carthage-2' Case: NABU Releases Details of Searches at SBU Major General Duka's Residence Ukrainian MFA Responds to Libya Regarding the Destruction of the Russian Corvette in Benghazi Foreign Currencies Rise in Ukraine: New Exchange Rates Recorded in Banks and Exchange Offices Uncertainty Over NMT-2027: 'Parents SOS' Highlights Risks of Admission Rules Delay Ukrainian MFA Responds to Libya Over Destroyed Russian Corvette Russia Plans to Launch Satellite with Nuclear Warhead Why Electricity Bills Don't Decrease During Power Outages Ukraine at UN: Withdrawal demands are not a path to peace

Multimillion-Dollar Costs and New Contracts: The Progress of the Military Memorial Near Kyiv

🎓 Education 2 min read 👁 2

Construction of the National Military Memorial Cemetery in the Kyiv region continues as project costs rise following non-tender agreements.

🎓Education

Key points

  • Additional contract worth 879 mln UAH signed without an open tender
  • Total estimated cost for the first phase increased to 3.02 bln UAH
  • Project adjustments include utility relocations and landscape changes

The construction of the National Military Memorial Cemetery in the Markhalivka forest within the Kyiv region continues to unfold amid ongoing discussions regarding its transparency and financing. The state institution acting as the project client signed an additional multi-million-hryvnia agreement with the previous contractor, the Building UA consortium, surpassing 870 million hryvnias. Notably, this substantial deal was concluded without holding open competitive procurement tenders, drawing scrutiny from civic observers.

Project Adjustments and Budget Growth

Following updates to the design documentation and mandatory expert reviews, the total estimated cost for the first phase of this high-profile national project has escalated to 3.02 billion hryvnias. The revised work schedule incorporates several alterations that directly impacted the final financial figures. These changes involve relocating engineering structures, modifying landscaping zones, and increasing the number of trees designated for removal.

  • relocation of the transformer substation and public facilities;
  • adjustments to engineering networks and utility routes;
  • expansion of green areas subject to clearance;
  • modifications to building finishes and exterior designs.

Available reports indicate that a significant portion of the initial funding has already been utilized for completed phases. However, the pattern of continuous budget expansions coupled with non-competitive contracting procedures underscores ongoing challenges regarding public oversight and financial accountability in state-backed infrastructural projects.

Source kyivschina24.com — kyivschina24.com/news/novyj-ministr-staryj-pidryadnyk-i-879-mln-bez-ten… ↗